Monday, June 27, 2016

Local Road Construction Update

SPOKANE COUNTY
Market Street (Parksmith to Farwell)- Road open to traffic with some work happening on the shoulder. This project installed sewer components, fiber optic and rehabilitated the roadway.

Seven Mile Bridge & Seven Mile Road- Detour in place with a temporary lowered speed limit of 25 mph while bridge is demolished and replaced. 

Hawthorne Road West (Waikiki to US395)- Road closed for road rehabilitation, including installing stormwater drainage swales, trees, irrigation, curbing and a bike lane.

Hawthorne Road East (US395 to US2)- Road will be closed completely on July 5. This project includes roadway rehabilitation, stormwater sand filters, curbing, bike lane and striping.

Houston Road from Colville Road to Grove Road- Crews are working on ditching, culvert and shoulder work during day hours only. No detours in place and the road is open to local traffic, bus traffic and emergency vehicles around the clock. For all other traffic, the road is closed from 6 a.m. to 5 p.m. 

WSDOT
US 2/Hayford Rd. Intersection-Eastbound drivers should be alert for lane restriction and some congestion as a developer constructs access to a business.

US 2-Division Street/Curb and Sidewalk- Northbound Division Street is reduced to two lanes to give crews room to work on curb and sidewalk improvements. Drivers may experience delays.

I-90/Westbound Freya Off-Ramp-Westbound drivers should be alert for narrow shoulders as crews construct a new westbound Freya Street off-ramp approximately 1/4 mile to the east of the current one.  All ramps open.  Expect lane restrictions on 2nd Avenue.

US 395-Division Street/Hawthorne Rd. Intersection- Be alert for some turn restrictions on Division as Spokane County work has Hawthorne Road closed between Division and Waikiki.

SPOKANE VALLEY
32nd Avenue from Dishman-Mica Road to University Road- Closed through mid-August for street preservation work. Signs detour traffic via Dishman-Mica Road and University Road.

32nd Avenue from University Road to Pines Road - Reduced to one lane in each direction through mid-August. The north sidewalk is closed. Anticipate brief interruptions to side streets and driveways from 7 a.m. to 5 p.m.

Fancher Road between Trent Avenue and Sharp Avenue - Traffic is reduced to one lane in each direction through early July.

Southbound Sullivan Road Bridge- Traffic is reduced to one lane northbound and two lanes southbound. Oversized vehicles should use Barker Road or Pines Road as alternatives. Turns from Indiana Avenue onto northbound Sullivan Road are reduced to one lane. Southbound Sullivan Road at Flora Pit Road will be reduced to one lane on weekdays through Friday, July 1 from 6 a.m. to 2 p.m.

SPOKANE CITY
Maple Street Bridge Lane Closure-Wednesday, June 29 one lane in each direction on the Maple Street Bridge will be closed. In celebration of the 25th anniversary of the Waste to Energy Facility employees will be painting the undercoat for a mural. In July artist Todd Benson will paint the mural.

Hazels Creek Stormwater Treatment Project-Freya Street is closed from 37th Avenue to Palouse Highway until early/mid-July. This project is located southeast of 37th Avenue and Rebecca Street. It will construct a stormwater treatment system with disposal ponds and stormwater piping.  
37th Avenue, Regal Street to Custer Street-  Due to a closure on Freya Street for the Hazel’s Creek Project, 37th Avenue will be closed east of Havana Street to Custer Street. The closure will NOT impact the intersection of 37th and Havana. This work is to reconstruct the road, include pavement replacement, curbs, sidewalk, bike lanes, stormwater piping, and a 36 inch water main.
      2016 Street Maintenance Curb Ramp Project- Work continues on Lyons Avenue from Perry St. to Pittsburg St. to install ADA compliant curb ramps.

Ben Burr Trail and Connection to the Centennial Trail- 
Work continues along the trail at Fiske and 11th Avenue with work progressing to the north. This project will construct a shared use paved trail connection for bicyclists and pedestrian as well as security lighting installation.  The project will be from the Centennial Trail at the Gonzaga Bridge southeast of Erie Street, continuing to Liberty Park where a connection will be made to the existing Ben Burr Trail. The trail will then continue on the existing Ben Burr Trail to the trailhead immediately south of Underhill Park.

Bridge Avenue and Monroe Street CSO Work-Summit Blvd/Bridge Avenue is closed to traffic. Lincoln has one northbound lane open.  Lincoln southbound is closed at Broadway with local access maintained to Anthony’s restaurant and parking lots. This project will construct a Combined Sewer Overflow Tank (CSO) tank and the necessary piping for our Cleaner River Faster Program.

Residential Chip Seal Work- The Residential Chip Seal Project will begin the actual chip seal application at the following locations and dates:
o   Kathleen Avenue Area (Indian Trail): Wednesday, June 29
o   Rebecca Street Area (Upriver Drive): Thursday, June 30
o   33rd Avenue Area (Comstock Park): Friday, July 1

During these days the roads will be closed to ALL traffic from 8 a.m. – 4 p.m.   No Parking signs will be in place. Surrounding residents will receive letters from the contractor a few days before the operation.

High Drive Phase II, Bernard to Grand Street Repair Work- Street repairs continue along High Drive. Traffic restrictions are in place and flaggers are on site to direct traffic.

Indiana Avenue from Dakota to Perry Street- The water department is conducting pre-construction work along this project.  Indiana will have temporary closures at times with a detour route during this scheduled work. This project will include curb ramps, storm swales, new curb, waterline replacement, signal installation work and some parking removal.

Main Avenue and Division Street Intersection Improvements- Work continues on sidewalk removal and excavation for underground storm water improvements.  Pedestrian detours are in place. There are lane restrictions on both Main and Division. Work on this project involves curb bumpouts at all four corners of Division Street and Main Avenue, the removal and replacement of existing curbs, gutters, and sidewalks, ADA upgrades, installation of planter boxes and planting.
Monroe/Lincoln Street Couplet, 8th Avenue to 2nd Avenue- This project reconstructs the roadway from 8th to 2nd Avenue and installs water facilities.  Crews have closed Monroe and Lincoln completely. The current two way traffic on Lincoln is open between 4th Avenue and 6th Avenue.  Access along 7th is through the work zone, but will be on unpaved surfaces.  There may be times when access along 7th Avenue will be restricted to limited hours during the day.  Monroe between 14th and 8th Avenue is open.   

The detour for through traffic is along 14th Avenue and Bernard/Washington/Stevens and 2nd and 3rd Avenue. The on ramp for eastbound traffic at Monroe is open.  Crews work from 7 a.m. to 10 p.m. six to seven days a week as needed. Expect more noise in the area during these hours.

Monroe and Lincoln Street, Main Avenue to 2nd Avenue- Starting Monday, June 27 at 10 a.m., Monroe will have two open lanes of traffic on the west side of the street.  After the morning commute, four way stop signs will be added at the intersections of 1st, Sprague, and Riverside Avenues beginning around 10 a.m. This is a full depth roadway replacement and full depth replacement between curbs on Lincoln Street and Monroe Street; Main Avenue from Monroe Street to Lincoln Street; and Monroe Street from Spokane Falls Boulevard to Main Avenue. 

Pettet Drive/TJ Meenach Combined Sewer Overflow (CSO 12) Project- This project will build a 690,000 gallon storage facility and connections to existing CSO Basin 10 outfall.Work also includes repaving of Pettet Drive and pedestrian/bike trail construction. 
Pettet Drive is closed to traffic until November. 
The clover leaf that services TJ Meenach, Down River and Pettit Drive (three out of the four legs) is open. The leg that comes off of Pettit north bound will re-direct citizens to Northwest Blvd. Vehicles traveling southbound on Down River Drive have two options; enter onto TJ Meenach or continue under the bridge and turn uphill to Northwest Blvd.

Rowan Avenue Improvements from Driscoll Boulevard to Monroe Street- The intersection of Alberta, Belt, and Ash will remain open to north and southbound traffic.  Rowan Avenue is open to traffic from Ash Street to Monroe Street.

Street Maintenance Grind and Overlay Work- Work continues on Indian Trail Rd. from Ridgecrest to the North City Limits. Flaggers will be closing one lane.  

Wellesley Freya Utility Work for Future WSDOT Roundabout- Water and sewer work is underway and expected to continue through the end of July.  This work is in preparation for a future roundabout being installed by WSDOT. Wellesley will be closed from Market to Rebecca.Freya will be closed from Broad to Longfellow.

No comments:


About SRTC

SRTC is the federally designated Metropolitan Planning Organization (MPO) for Spokane County. Urbanized areas with populations exceeding 50,000 people are required to have an MPO. SRTC was formed to address the county's transportation planning needs. It provides coordination in planning between the public, cities, small towns, the county, the state, transit providers, and tribes.

SRTC offers services including transportation monitoring, transportation modeling, census information analysis, travel demand forecasting, historical traffic count analysis, geographic information systems, and trip generation rates.